The Federal Aviation Administration has approved Boeing’s production certificate for the new 737 MAX North Line in Everett, Washington. The production certificate will enable Boeing to ramp-up production at its new facility. The North Line will specialize in the recently certified 737 MAX 10, the largest model in the series. The existing 737 facilities in Renton will continue with its three final assembly lines, with the North Line adding a fourth line for a 25% capacity increase over the long-term.

MAX 10
image Boeing

Boeing has been space constrained at its Renton facility, which has tight clearance with overhead constraints in that older facility. The new $1 billion line in Everett utilizes much larger bays originally used for the 747 and 787 production. The new facility began operations in July, and rolled out its first 737 MAX 10 for WestJet in late October. Boeing is currently producing eight aircraft moving through the production process in the new facility.

One Hurdle Remaining after Production Certificate

Production certificate approval for the new line means that only one hurdle remains for deliveries of the MAX 10 to begin. That hurdle is Boeing passing an FAA audit of the new production line. This is a familiar process for Boeing, and one we would expect they should pass before year end.

Boeing Commercial Airplanes CEO Stephanie Pope stated “We have three priorities in Boeing Commercial Airplanes, and one of them is to deliver safe and quality airplanes to our customers on time. This investment builds capacity and resiliency into our factory and our production system.”

Future Production Increases

Boeing has stabilized production of the 737 MAX in Renton at 47 aircraft per month. The North Line in Renton will enable the company to ramp-up to 52 per month in 2027, while providing additional capacity for future growth. The production capacity at Everett could reach 20 plus aircraft per month as the line reaches maturity.

The Bottom Line

Boeing’s production certificate for the new facility completes a critical milestone. While Boeing has done this many times before, the increased scrutiny by the FAA after the January 2024 missing bolts incident tightened the requirements. With the production certificate now in place, deliveries of the long-delayed MAX 10 will soon begin.

Deliveries generate cash flow, and this milestone is an essential step as Boeing raises its aircraft production for 2027. We fully expect the new line to continue to expand over the next few years as the popular MAX 10 will ramp-up in Everett. With a backlog of nearly 1,700 MAX 10 models, the new facility should be busy for the foreseeable future.