Boeing 737 MAX Deliveries Hit by Quality Glitch

Care to share?

That quality escape thing rears its ugly head again. But it appears to be a minor issue caused by an internal problem.  The news of the quality escape drowns out the excellent news that Boeing is delivering faster Airbus.

What Happened
Boeing

disclosed the issue on March 10, describing it this way: “Our 737 programme is performing rework on a group of airplanes to fix wires that have small scratches due to a machining error. This ensures they meet our quality standards before the airplanes are delivered.” The machining error originated at Boeing’s own Renton, Washington, facility — not a third-party supplier.

Delivery Impact
In March, through yesterday, Boeing performed 19 MAX first flights and made 5 deliveries. This is far slower than usual. There was a ~10-day delivery halt. Boeing maintained production at roughly 42 aircraft per month and has not revised its 2026 full-year delivery goal of 500 737s.